Clearways Yard, Belfast Harbour – Electrical System Controls

Client: Clearways
Project length: 30 months
HF divisions involved: Electrical, Automated Controls

We are about to start on-site works for complete shredder plant and ancillaries at Ireland’s largest scrap processing plant located at Clearways main yard in Belfast harbour.

This will be a full scale system integration of all electrical aspects of plant from 33kV design/supply and installation down to optical Ethernet networks and PLC control system.

Project Time: 24 months (development and design), 6 months installation

Contract value: £750 ,000

 

 

Return to Case Studies >>>

Return to Latest News >>>

CASE STUDIES

Discover examples of project work we have done in all our sectors.

LATEST NEWS
HF Comms Ltd achieve ISO 45001:2018 Health & Safety Standard

HF Comms Ltd are delighted to announce that, we have successfully achieved certification to the new ISO 45001:2018 Health and Safety standard. Leadership and Worker Participation were key to achieving the standard, and by working together we strive to provide “a safe place to work” for all our employees and those affected by our works. […]

  • ACCREDITATIONS

  • Private Login