Clearways main yard in Belfast harbour

We are about to start on-site works for complete shredder plant and ancillaries at Ireland’s largest scrap processing plant located at Clearways main yard in Belfast harbour. This will be a full scale system integration of all electrical aspects of plant from 33kV design/supply and installation down to optical Ethernet networks and PLC control system.

Project Time
24 months (development and design), 6 months installation

Contract value
£750 ,000